Client: Our Lady's Hospital
Project: Category 3 Laboratory
Size: 100 sq metres
Project Timeframe: 14 weeks


Requirement:


The Category 3 Laboratory formed part of the Hospital’s ongoing development programme & by late summer 2006, Our Lady's Hospital were searching for a supplier to help expedite the project.

Solution:

Roan Building Systems were awarded the design & build contract for the construction of the new Laboratory, an Off-site constructed Category 3 Laboratory. Build quality (a structural design life in excess of 60 years), a proven ability to deliver on a short timeframe & a strong working relationship with both the client & architect were all important factors in the appointment of Roan Building Systems as the contractor.

As main contractor Roan Building Systems were also responsible for PSCS & PSDP. This highly specialised building required full clean room certification as part of the contract.

Scope of Works:

  • Civil works: reducing level, foundations, connection to services & links to main hospital building
  • Mechanical & Electrical fit-out
  • Medical Gases
  • Fire Detection & Suppression Systems
  • Extension of existing hospital heating systems
  • Partitioning
  • Suspended Ceilings
  • Air-conditioning/ extraction systems
  • Floor covering including coved skirting
  • Decoration
  • Project supervision of all contractors
  • Clean room certification

Innovative Solutions:

The complete off-site fitout of the ward expedited the programme time greatly. The off-site construction of the building also greatly reduced the health & safety risk:
- Significantly reduces the number of vehicle movements on site
- Greatly reduced the threat of aspergillious by reducing the onsite construction element
- Reduced working at height requirements

The 16 week programme timeframe was over 50% faster than that offered by traditional building methods. Precise project management by Roan Building Systems experience team ensured this ambitious target was achieved.

Image Gallery:

(click image for larger view) (click image for larger view) (click image for larger view)
(click image for larger view) (click image for larger view) (click image for larger view)

 

 

Roan Building Systems Brochure
Marketing Suites
Warrenty Protection
Hospital Trailer

Copyright © 2010 Roan Building Systems ™ All Rights Reserved


Home | Hire | Contact Us  

Roan Building Systems, Monckton Road Industrial Estate, Denby Dale Road, Wakefield, WF2 7AL.
Call Today: 0845 121 1687 | Email: sales@roanbuildings.co.uk


Siteserv Group Companies:
Website Designed by: Web Creations