| Client: |
Accident & Emergency Ward |
| Project: |
Dignity Suite/ Nightingale Accident &
Emergency Ward |
| Size: |
800 sq metres |
| Project Timeframe: |
16 weeks |
Requirement:
With Accident & Emergency waiting times
reaching crisis point. The Hospital proposed
the Nightingale Ward to help alleviate the backlog.
The Hospital soon commissioned leading architects,
RKD, and the search began to find the perfect
supplier.
|
Solution:
After a rigorous tender process, the state-of-the-art
RoanPlan Modular Building from Roan Building Systems
was selected to house the new 41 Bed Transition Lounge.
This new ward would be annexed to the current Accident
& Emergency Department, which links to the main
hospital street.
As main contractor, Roan Building Systems were also
responsible for PSCS & PSDP.Infection control
is a critical issue when working in a live hospital
environment, all site personnel were required to adhere
to Roan Building Systems strict infection control
policy.
The new 800sq mtr ward was constructed off-site &
craned into position. The lift & installation
was completed in one day & was clad to blend in
seamlessly with the main hospital. As infection control
measure the link between the new department &
the main Intensive Care Ward corridor was not broken
through until the modular building was complete.
Scope of Works:
-
Civil works: reducing level,
foundations, connection to services & links
to main hospital building
-
Mechanical & Electrical
fit-out
-
Medical Gases
-
Nurses call facility
-
Bed-head trunking
-
Fire Detection & Suppression
Systems
-
Extension of existing hospital
heating systems
-
Mechanically operated sky lights
-
Partitioning
-
Suspended ceilings
-
Floor covering including coved
skirting
-
Decoration
-
Project supervision of all contractors
Innovative Solutions:
The complete off-site fitout of the ward expedited the
programme time greatly. The off-site construction of
the building also greatly reduced the health & safety
risk:
- Significantly reduces the number of vehicle movements
on site
- Greatly reduced the threat of aspergillious by reducing
the onsite construction element
- Reduced working at height requirements
The 16 week programme timeframe was over 50% faster
than that offered by traditional building methods. Precise
project management by Roan Building Systems experience
team ensured this ambitious target was achieved.
Image Gallery:
|
 |
 |
| (click
image for larger view) |
(click
image for larger view) |
(click
image for larger view) |
|
|
|
|
|
 |
| Copyright
© 2010 Roan Building Systems ™ All Rights
Reserved |
|
|
| Home
| Hire | Contact
Us |
|
Roan Building Systems, Monckton Road Industrial Estate, Denby
Dale Road, Wakefield, WF2 7AL. Call Today: 0845
121 1687 | Email: sales@roanbuildings.co.uk |

| Siteserv
Group Companies: |
 |
 |
 |
 |
 |
 |
 |
|
| Website Designed
by: |
 |
Web
Creations |
|
|
|